Need a fire-rated wall for a kitchen, shop or commercial unit? Start with the required fire resistance and the approved design—not just a choice between blocks and boards. A 1-hour or 2-hour wall needs the correct construction, protected openings and supporting documents. Your Qualified Person (QP) should establish the applicable SCDF Fire Code requirements before installation.
“Can quote a two-hour partition?”
Before comparing prices, ask: where does the wall go, what does it separate, and which drawing specifies two hours? A kitchen enclosure, a tenant boundary and an ordinary office divider can have different requirements.
What does a 1-hour or 2-hour fire rating mean?
A 1-hour rating refers to 60 minutes; a 2-hour rating refers to 120 minutes. These periods relate to the relevant criteria under a standard fire test. They are not a promise that occupants can safely remain beside a real fire for that length of time.
SCDF defines fire resistance as a property of a building element. The relevant criteria include stability, integrity and insulation. This is why a board labelled “fire resistant” does not, by itself, establish the rating of the finished partition. [1]
The required period depends on the building and the element’s function. Clause 3.3.2 refers to purpose group and building dimensions, alongside specific requirements elsewhere in the Fire Code. A contractor should not choose one hour or two hours simply because it is the usual quotation. [2]
Fire-rated block wall or drywall partition: what should you compare?
| Item to confirm | Block or masonry wall | Fire-rated drywall partition |
|---|---|---|
| Construction specification | Exact block type, thickness, construction and applicable finishes | Exact system, boards, framing, insulation where specified, fixings and joint treatment |
| Supporting evidence | Applicable design evidence; Annex 3A where relevant | System certification, technical details and applicable test or assessment evidence |
| Site checks to request | Supporting structure, junctions, openings and wall condition | Permitted height, framing, board layers, junctions and service arrangements |
| Quotation detail | Identify the proposed wall construction | Identify the complete system rather than quoting only a board brand |
For masonry, SCDF’s Annex 3A distinguishes construction types and load-bearing conditions. Avoid accepting “100 mm block wall equals two hours” without confirming the applicable construction and evidence. [3]
For drywall, manufacturers offer different systems for different performance requirements. Knauf’s Singapore guidance specifically advises checking the technical documentation for each system. Do not assume that adding another board layer converts any partition into a compliant 2-hour wall. [4]
See 9RENO’s fire-rated partition wall service for the related installation enquiry.
What do commercial kitchens need: open flame or non-flame cooking?
Tell the QP what equipment will actually be installed. “Café”, “central kitchen” or “pantry” is not enough information to settle the fire-safety design.
| Proposed kitchen use | What needs checking |
|---|---|
| Gas cooking or charcoal grilling | Apply the open-flame provisions to the actual layout and equipment |
| Induction or other cooking with no open flame | Check the non-open-flame provisions and any applicable special consideration; do not assume automatic exemption |
| Food preparation or reheating area | Provide the appliance list and intended use for assessment |
| Kitchen using LPG | Include the gas installation in the design review; wall works alone do not resolve LPG requirements |
Kitchens with open-flame cooking
Under Clause 3.2.5f, rooms or spaces with open-flame cooking, except residential units in Purpose Groups I and II, generally require separation by walls and floors with at least 1-hour fire resistance. The clause sets out specified exemption conditions, including approved extinguishing systems covering all cooking facilities. Those conditions need project-specific checking. [5]
SCDF’s kitchen guidance identifies a minimum half-hour fire-rated door opening outward from the kitchen. This kitchen provision must not be turned into a blanket rule that every fire door needs only half the wall’s rating. [5, 7]
Kitchens without open-flame cooking
Table 6.4A lists kitchen compartmentation and door requirements and identifies special consideration for kitchens without open-flame cooking appliances, or with approved extinguishing systems covering all cooking facilities. Special consideration does not mean every induction kitchen can omit a fire-rated enclosure. Ask the QP to confirm the applicable design. [6]
A 2-hour kitchen wall may still be specified for the particular boundary or project. Do not reduce a drawing’s requirement to one hour just because the general open-flame kitchen provision mentions one hour.
Check doors, service openings and the top of the wall
A compartment wall must form a complete fire barrier. SCDF’s Clause 3.7 addresses protected openings and fire-stopped junctions. The wall, door opening and service routes need to work together. [7]
Before closing up, ask the project team to confirm:
- The wall’s full extent and its junction with the structure above.
- The specified fire door, frame and any access-panel details.
- Protection around pipes, cables and other permitted penetrations.
- Which joints and concealed details need inspection records.
For services incorporated within fire-rated drywall, Clause 3.3.6b requires the installation to stay within the tested arrangement. It also requires electrical cables within the dry construction to be in metal conduits and prohibits gas pipe installations within it. Kitchen exhaust penetrations require their own applicable design details. [8]
CoC, DoC, FSC02 and NOA: which document does what?
These documents serve different purposes. One is not a substitute for the others.
| Term | Meaning and purpose |
|---|---|
| SCDF | Singapore Civil Defence Force, which administers the fire-safety framework and relevant approvals |
| CoC / COC | Certificate of Conformity: issued by an accredited Certification Body for a regulated fire safety product meeting the relevant requirements |
| DoC / DOC | Declaration of Compliance: batch-related information for certified regulated fire safety products; required for specified product categories |
| FSC02 | Regulated Fire Safety Products Installation Certificate: the installation certification form listed in SCDF’s forms and guides |
| NOA | Notice of Approval: plan-approval documentation; it is distinct from the completion-stage FSC |
| FSC | Fire Safety Certificate: issued following completion of the project’s fire safety works and the applicable certification process |
| TFP | Temporary Fire Permit: permits use for a limited period under the applicable conditions before the FSC |
| QP / RI | Qualified Person / Registered Inspector: the professionals involved in the applicable design, submission and inspection process |
For regulated products, the QP must verify a valid CoC, an exact product match and the required serial labels or DoCs. Check applicability against Chapter 11 and Table 11A rather than assuming every block wall needs the same paperwork as a proprietary drywall system. [9]
DoC means Declaration of Compliance in current SCDF guidance. Avoid calling it “Declaration of Conformity” in the quotation or handover checklist. FSC02 also does not mean the same thing as an FSC. [9, 10]
What is the approval and installation sequence?
- Confirm the use and layout. Provide the existing plans, intended activity, cooking equipment and landlord requirements.
- Establish the submission route. The QP checks whether plan approval, a qualifying Minor Additions/Alterations lodgement or an exemption applies. SCDF states that plan approval is required before work starts in other cases. [11]
- Agree the wall specification. Record the rating, construction, openings, service details, inspection stages and document responsibilities.
- Install and record the work. Arrange the inspections and records required by the QP and system requirements before relevant details are concealed.
- Complete the applicable certification. The QP coordinates the completion application and RI inspection requirements. An NOA or a supplier’s CoC alone does not establish that the completed premises have obtained an FSC. [12]
What should your fire-rated wall quotation include?
Ask for a scope that identifies:
- Wall location, length, height and required fire resistance.
- Proposed block construction or named drywall system.
- Doors, frames, access panels and service penetrations.
- Junction details and fire-stopping work.
- Protection, demolition, disposal and making good.
- Product evidence, applicable CoC/DoC and FSC02 responsibilities.
- Whether QP services, submission, RI inspection and other trades are included or separately appointed.
A price per square metre is only useful when these items are clear. Ask for exclusions in writing before comparing quotations.
FAQs
Can drywall achieve a 2-hour fire rating?
Yes, suitable systems are available. The specified assembly and installation must meet the project requirements; the board description alone is insufficient. [4, 8]
Does a kitchen always need a 2-hour block wall?
No universal rule establishes that. The kitchen provisions, building conditions and particular compartment boundary must be checked before choosing the rating or construction. [2, 5, 6]
Can I use ordinary silicone around a service opening?
Do not substitute it for the specified fire-stopping detail. Ask for the applicable tested or approved penetration and junction arrangement. [7]
Does a CoC mean the completed wall has SCDF approval?
No. Product conformity, installation checks, plan approval and completion certification have different roles. Keep the applicable documents together. [9, 11, 12]
Can I change the cooking equipment after the layout is approved?
Refer the change to the QP before installation or use. Moving from non-open-flame equipment to gas or charcoal cooking needs a fresh review of the applicable requirements. [5, 6, 11]
Planning a fire-rated wall in Singapore?
Send 9RENO your layout, wall dimensions, site photographs and any QP drawings or landlord requirements. For a kitchen, include the cooking equipment list and whether gas, charcoal or non-open-flame appliances will be used.
We can discuss the installation scope and the professional coordination needed for your project. The applicable design and approval requirements must be confirmed before work proceeds.
Discuss your fire-rated wall project with 9RENO or WhatsApp +65 9858 3011.
This guide explains planning considerations. Project specifications and submissions must follow the applicable Fire Code provisions, amendments and approved design.
Sources for the article
Official SCDF guidance checked on 23 November 2026. Manufacturer information is illustrative and does not select a product for the project.
- SCDF Clause 1.4 — fire resistance definitions: https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-1-general/clause-1.4-definitions
- SCDF Clause 3.3 — required fire resistance: https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-3-structural-fire-precautions/clause-3.3-fire-resistance-of-elements-of-structure
- SCDF Annex 3A — notional periods of fire resistance: https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-3-structural-fire-precautions/annex-3a
- Knauf Singapore — drywall systems and specification guidance: https://knauf.com/en-SG/systems/drywall-systems
- SCDF Clause 3.2.5f — kitchens: https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-3-structural-fire-precautions/clause-3.2-provision-of-compartment-walls-and-compartment-floors
- SCDF Table 6.4A — kitchen compartmentation and special consideration: https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-6-firefighting-systems/related-tables-and-diagrams-of-chapter-6
- SCDF Clause 3.7 — compartment walls, openings and junctions: https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-3-structural-fire-precautions/clause-3.7-compartment-walls-and-compartment-floors
- SCDF Clause 3.3.6 — fire-rated board construction and services: same URL as source 2.
- SCDF Regulated Fire Safety Products — CoC, DoC, labels and QP checks: https://www.scdf.gov.sg/fire-safety-services-listing/plans-submission-process/regulated-fire-safety-products
- SCDF Forms and Guides — FSC02: https://www.scdf.gov.sg/fire-safety-services-listing/downloads/forms-and-guides
- SCDF Plan Approval: https://www.scdf.gov.sg/fire-safety-services-listing/plans-submission-process/plan-approval
- SCDF Fire Safety Certificate & Temporary Fire Permit: https://www.scdf.gov.sg/fire-safety-services-listing/plans-submission-process/fire-safety-certificate-temporary-fire-permit